Owner: City of Rocky Mount
Project Name: Old Mill Road Sewer Pump Station Replacement & Force Main CRM Bid Number: 320-290722RP
Project Number: 20-154
Project Description:
Description:
Part A – Construction of Proposed 3,820 gpm Triplex Sanitary
Sewer Pump Station including but not limited to:
·         Reinforced, Cast-in-Place Concrete Wet Well and Dry Well
·         Three (3) Self-priming Sewage Pumps and controls
·         Split-face CMU Pump Station building with Standing Seam Metal Roof
·         Electrical including Stand-by Generator
·         Site Work
·         14-inch Ductile Iron Force Main with Bypass Pump Connections
        and Tie-in to Existing 8-inch PVC Force Main
Part B – Pump Station Force Main including but not limited to:
·         3,290 LF 14-inch PVC C900 (DR-21) Force Main
·         140 LF 14-inch Ductile Iron Force Main
·         200 LF 14-inch Restrained Joint Ductile Iron Force Main
·         605 Horz. Feet 14-inch ID Directional Bore (Rock)
·         400 Horz. Feet 14-inch ID Directional Bore (Dirt)
·         70 LF 30-inch Diameter Steel Casing (Bored and Jacked)
·         5 EA Sewer Air Release Valves
·         150 CY Rock Excavation (Contingency Item)
·         Erosion Control Measures
Pre-Bid Conference Location:

 

 

Bid Opening Date: Thursday, October 13th, 2022 - 2:00 pm
Bid Opening Location:
Place of Opening: City of Rocky Mount
Purchasing Office
Frederick E. Turnage Administrative Services Complex
Third Floor Committee Room
331 South Franklin Street
Rocky Mount, NC 27804

Re-Advertisement

Plans Available at:
Plans Available at:
Green Engineering, P.L.L.C – Wilson, North Carolina
City of Rocky Mount – Rocky, North Carolina
ConstructConnect – Plan Room – Online Service
Plan Deposit: 150.00
Refund Policy:
Refund Policy:
Non-Refundable
Project Documents:

BIDDERS LIST

Addendum No. 1

Re-Advertisement